About the project
- Client: Low Whiteside
- Category: Wind
- Enercon E33 – 330kW
- 37 metre hub height
- Estimated annual output – 750,000kWh
- Project size - <£1m
- 37 metre hub height
- Estimated annual output – 750,000kWh
- Project size - <£1m
This project required a 3 km grid connection cable to be installed in collaboration with a number of neighbouring wind turbines and by agreement with South Lanarkshire Council. The turbine now produces more than 750,000kWh of clean energy every year - offsetting over 300,000kg of CO2 per annum.